Fourteen companies attended a pre-selection briefing for the operator of the Phase 3-2 automated container terminal at Gwangyang port in South Jeolla Province.
The Yeosu Gwangyang Port Authority held the briefing Tuesday at Shilla Stay Yeosu, presenting its automated terminal construction plans and operator recruitment conditions to about 50 representatives from 14 domestic and foreign shipping lines, port operators and logistics firms.
The Phase 3-2 automated container terminal at Gwangyang port will comprise four berths with a quay wall stretching 1,300 meters, with a target opening in the first half of 2029.
The operating terms set the integrated facility and equipment lease at 38.5 billion won ($29.1 million) per year as of 2029, with a lease period of 30 years.