Tombs and artifacts from the Three Kingdoms and Joseon periods unearthed
Excavation and road construction to proceed simultaneously
Construction of the Ulsan Nongso-Gangdong road — a bypass route being built to ease congestion on National Highway 31 and scheduled for completion in January 2031 — faces unavoidable delays in some sections after the discovery of buried cultural artifacts.
Ulsan City held a press conference Tuesday on the cultural heritage investigation along the Nongso-Gangdong road corridor, announcing it would pursue excavation and road construction simultaneously to protect the buried heritage. The project involves building an 11.1-kilometer, four-lane road from Gadae-dong to Sanha-dong in Buk-gu, Ulsan, at a total cost of 620.9 billion won ($465 million).
The project was selected in 2019 as exempt from a preliminary feasibility study under the national balanced-development initiative. Ground-breaking took place in October 2024, with completion set for January 2031. Construction is currently divided into four sections, with overall progress at 4 percent.
Before breaking ground, the city conducted a surface survey in April 2022 covering the entire 942,971-square-meter project zone. The Cultural Heritage Administration determined that 12 sub-zones totaling 234,360 square meters — about 25 percent of the total area — required further investigation. Trial excavations have since been completed across three of those sub-zones, covering 87,761 square meters, uncovering 97 archaeological features in all, including Three Kingdoms-era stone-lined tombs, Joseon-period building sites and pit graves, and a well of unknown age.
Of that area, 18,872 square meters have either received or are expected to receive notification from the Cultural Heritage Administration requiring full-scale excavation. Ulsan City said it will carry out all legally required investigations of buried cultural heritage and implement any preservation measures called for following the administration's review.
"Some delays in the construction schedule are unavoidable given the cultural heritage investigation within the Nongso-Gangdong road corridor," Oh Se-guk, head of Ulsan City's General Construction Headquarters, said at the press conference. "We will closely manage the construction progress and investigation schedule to minimize the impact of the heritage survey on the overall timeline."