Bucheon sits on W3b in dormant grants for 7 years as traditional markets face clawback

by
Lee Hong-seok
Published : Nov. 27, 2026 - 10:19:22
    • Copy Completed!

View Korean Original

Bucheon lawmaker Yun Dan-bi criticizes poor pre-consultation and lax deadline extensions at audit

Jeeil Market's 4.83 billion won facility budget goes entirely unspent while city pays bond interest

Hansin and Wonjong markets mirror the pattern with zero execution

Bucheon Jeeil Market
Bucheon Jeeil Market

Bucheon has failed to spend a single won of the 3 billion won ($2.23 million) in Gyeonggi Province special adjustment grants it secured in 2019 for an arcade installation at Bucheon Jeeil Market, leaving the city at risk of having to return the funds seven years on.

Yun Dan-bi, chair of the Bucheon City Council's Finance and Culture Committee, said at an administrative audit of the Economy and Environment Bureau on Wednesday that the city had allowed the project to drift for years despite securing a large budget, never managing to disburse the provincial funds.

Yun said the core reason for the delay was the city and market vendors' failure to reach agreement on how long traders would have to suspend business during the utility-relocation work that must precede the arcade installation. Because no deal could be struck on the number of closure days — a matter directly tied to vendors' livelihoods — the project has remained in limbo.

Yun said the city had pushed ahead to secure the provincial grant before carefully gauging the maximum business-closure period vendors could accept, applying for the funds without that groundwork in place.

Yun also said that when the city extended the project deadline twice for a combined two years, it failed to rigorously review what had actually been resolved during each extension period and whether a ground-breaking had become feasible — a procedural step neglected each time.

The city's 2025 settlement accounts bear this out: the 4.83 billion won earmarked for the Jeeil Market arcade facility was recorded as entirely unspent, with zero execution.

With construction never having started, the city has been left servicing the principal and interest on local bonds issued for the project, effectively burning taxpayer money on interest alone.

The problem of grants sitting frozen due to inadequate pre-consultation was not confined to Jeeil Market.

Settlement data for fiscal year 2025 show that Bucheon received a combined 642 million won in special adjustment grants last year — 500 million won for Hansin Market and 142 million won for Wonjong Jungang Market.

Delays in negotiations with merchant associations and unresolved on-site conditions meant neither project spent a single won within the year, and the full amounts were carried over to the following fiscal year.

After the city council repeatedly flagged deficiencies in on-site reviews and resident-consent procedures, city officials said they would conduct phased feasibility checks before breaking ground on major facility projects, and marked the recurrence-prevention measures in this year's audit materials as "completed."

Yun pushed back on that characterization. "Rather than simply recording that paperwork has been completed, the city must proactively confirm — at the budget application stage itself — what impact construction will have on vendors' businesses and what closure terms they can accept," Yun said. "Build an administrative system that rigorously verifies, each time a deadline is extended, exactly which outstanding issues have been substantively resolved compared with the previous extension."