Ulsan tram depot to move to science museum site

by
DONG-SOON PARK
Published : Nov. 26, 2026 - 15:39:10
    • Copy Completed!

View Korean Original

Project extended by 2 years, completion now set for 2030

Public hearing held Friday; to be reflected in master plan

Section-by-section and nighttime construction to minimize disruption

A route map of Ulsan Urban Railway Line 1 showing the depot relocation. The depot will move from its originally planned site near Taehwagang Station in Samsan-dong (blue) to a site south of Ulsan Science Museum in Okdong (red). [Provided by Ulsan City]
A route map of Ulsan Urban Railway Line 1 showing the depot relocation. The depot will move from its originally planned site near Taehwagang Station in Samsan-dong (blue) to a site south of Ulsan Science Museum in Okdong (red). [Provided by Ulsan City]

The depot for Ulsan Urban Railway (tram) Line 1 will be relocated from Taehwagang Station to the Ulsan Science Museum site, the city confirmed. The depot serves as a garage and operations base for tram vehicles, handling inspection, maintenance and cleaning.

Ulsan revised its master plan to move the depot from a 23,595-square-meter plot at Taehwagang Station Plaza in Samsan-dong, Nam-gu, to a 20,098-square-meter site on the southern side of Ulsan Science Museum in Okdong, Nam-gu.

The station plaza sits on soft ground averaging 24 meters deep and has high-pressure gas lines and other underground infrastructure buried beneath it. Soil improvement, utility relocation and depot construction combined would require at least 72 months, and project costs were projected to rise by 30 billion won ($22.3 million).

The science museum site, by contrast, sits on bedrock and requires no ground improvement. With no major underground obstructions, depot construction — including land compensation — can be completed in 27 months. The site also offers good access to the main line and, being set apart from the city center, would minimize impact on the urban streetscape.

The completion timeline has been pushed back two years, from the original 2021–2028 window to 2021–2030, to account for pre-construction administrative procedures including design work, various impact assessments and consultations with relevant agencies.

The route length will shrink by 92 meters — from 10.850 kilometers to 10.758 kilometers — following adjustments to the start and end points, and some of the 15 stations will be repositioned. Total project costs are expected to rise from 381.44 billion won to 382.47 billion won, an increase of 1.03 billion won, with 60 percent covered by the national government and 40 percent by the city.

To minimize disruption during construction, the city will maintain at least three lanes in one direction on Samsan-ro and at least two lanes in one direction on Munsu-ro and Daehak-ro. Work will proceed in segments and be carried out partly at night.

Ulsan held a public hearing for experts and residents Friday at the Citizens' Hall on the first floor of the Ulsan City Council building, as required under Article 6 of the Urban Railway Act. Officials presented the revised master plan and a draft environmental impact assessment, then gathered public input through discussion and a question-and-answer session.

Residents who could not attend the hearing may submit written comments to the city's Metropolitan Tram Transportation Division by Dec. 4 — by visiting in person, by mail, by fax at 052-229-7779, or by email at abkeun@korea.kr.