Overall construction 80% complete, civil works at 94%
Sinkholes and cost overruns push completion to end of 2027
Busan Transportation Corporation announced Tuesday that tunneling has been completed across the entire main-line section of the Sasang–Hadan urban rail project. Corporation President Kim Tae-ho walked the full length of the line on Monday to inspect construction progress and on-site safety management.
The project involves building 847 billion won ($629 million) worth of infrastructure along a 6.9-kilometer corridor, including seven stations and one depot. Overall construction stands at 80 percent complete, while civil works on the main-line structures have reached 94 percent.
The Sasang–Hadan line has long been a priority for residents of western Busan. The line will connect Sasang Station on subway Line 2 — a major transit hub served by the intercity bus terminal and the Busan-Gimhae Light Rail Transit — with Hadan Station on Line 1, improving urban rail access across the western part of the city.
The project traces its origins to a Busan city transportation improvement plan drawn up in the early 2000s. It cleared a preliminary feasibility review in March 2010, and the master plan was finalized and officially announced in January 2013. Construction began in earnest in December 2015 with the signing and ground-breaking of turnkey contracts for sections 1 and 5, followed by the ground-breaking of section 3 in July 2016.
The project has not been without setbacks. A rockfall incident halted work at one point, and a series of large sinkholes opened along the construction corridor. Changes to the route plan — including the addition and relocation of stations and the relocation of the depot — pushed additional construction costs up by about 136.6 billion won. The administrative process of negotiating the revised total project cost with the Ministry of Economy and Finance pushed the completion date back by one year, from the end of 2026 to the end of 2027.
After personally inspecting the main-line structures on Monday, Kim urged workers to stay vigilant. "Civil works are entering the final stretch, but we must not let our guard down and must remain alert to safety incidents that can occur during construction," he said. "Every worker should strictly follow safety rules and see the remaining work through to the end."
Although civil works are winding down, additional construction remains before the project is complete, including work on the stations and the depot. Busan Transportation Corporation said it plans to manage schedules carefully to keep each phase of work on track while also stepping up efforts to prevent on-site accidents.